Improvements to Fruitvale Station in June and July
Beginning Monday, June 25 and continuing through the end of July, crews will be working on improvements to the bus access and sidewalks at Fruitvale station. These improvements will require that some bus stops be relocated while the work is being done.
The work will be conducted in two (2) phases (download the Passenger Bulletin for locations .pdf):
Phase 1: Close the bus stop (temporary stops will be located along San Leandro Street, 35th Avenue, East 12th Street, and the taxi stand) and replace the concrete bus pad, replace the sidewalk at the plaza, repave asphalt concrete and install a decorative crosswalk. (Work will take approximately 28 days).
Phase 2: Close off the taxi area and replace the sidewalks and install a new decorative crosswalk. (Work will take approximately 10 days).
We apologize for any inconvenience this may cause you and appreciate your patience.
If you need language assistance services, please call BART’s Transit Information Center at (510) 465-2278.
Updated Monday, June 25, to correct temporary bus stop locations in text and in downloadable PDF of map.